Reconstruction of TG1, TG2 a TG3 control system and excitation after floods in VE Štěchovice.

Auftraggeber:
ČEZ, a.s. Vodní elektrárny (Major supplier – VA TECH HYDRO)


Ausführung:
01/2003 - 08/2004


Leistungen:
  1. Dismantle the existing equipment and control system cabling
  2. Install new control system cabinets and exciting assemblies TG1, TG2 and TG3, cabling and instrumentation

 
 